F-M High School construction nears the halfway mark

This winter, construction on the $52 million capital improvement project at Fayetteville-Manlius High School is expected to reach the halfway point. Project construction began in summer 2023.

  • students sitting at tables in a modernized classroom which features a geometric ceiling design
    State-of-the-art classroom in the new STEM wing addition.

Completed work

  • Turf field replacement
  • Track resurfacing
  • Science, technology, engineering and math (STEM) wing addition
  • Main office suite consolidation in House 1, including new nurse’s office
  • Staff lounge renovation
  • Kitchen upgrades
  • Roof replacement
    • Art wing
    • Library Media Center
  • House 2 boiler replacement
  • Crawlspace asbestos abatement

Ongoing work

  • Cafeteria expansion
  • Existing cafeteria renovations
  • Broadcast journalism and student support space addition
  • Wellness Center renovations
  • Auxiliary gym renovations
  • Photography classroom renovations
  • Courtyard renovations, including outdoor seating addition
  • Public address system replacement
  • Fire alarm replacement

The majority of the ongoing work is focused on renovating and expanding student spaces.

Remaining work

  • House 2 old main office and old nurse’s office conversion into classroom space
  • House 2 HVAC upgrades
  • House 2 ceiling replacement and select flooring replacement
  • HVAC replacement
    • Auditorium
    • Music classrooms
    • House 1 gym
  • Library Media Center skylight replacement
  • House 1 window/entrance replacement (north entrances)
  • Science wing roof replacement

Construction is expected to be substantially completed by fall 2026.